EntelliGuard R Circuit Breaker Retrofill AKD-5 Installation Manual DEH-41547 02/12

Figure 22. AKD-5—Cassette or Substructure, Racking and
Removing Tool

Figure 23. AKD-5—Cassette or
Substructure, Now Racked In

Install Lock Bracket

It must be ensured that the supply power

to the compartment is turned off/

compartment is de-energized for all the

incoming and outgoing circuits of the LVS

prior to any work being conducted on it.

During the installation and related work on

the equipment, it must be ensured that the

operator is using the prescribed PPE for the

specified tasks.

Ensure only qualified personnel install, operate, service, and maintain all electrical

equipment.

1. Check that the retrofitted EntelliGuard cassette has been completely racked into the cabinet.
2. Slide the bracket back into position as shown in the image below (

Figure 24)

and line up the holes

previously drilled with the holes on the locking bracket (

Figure 25).