Figure 22. AKD-5—Cassette or Substructure, Racking and
Removing Tool
Figure 23. AKD-5—Cassette or
Substructure, Now Racked In
Install Lock Bracket
• It must be ensured that the supply power
to the compartment is turned off/
compartment is de-energized for all the
incoming and outgoing circuits of the LVS
prior to any work being conducted on it.
•
During the installation and related work on
the equipment, it must be ensured that the
operator is using the prescribed PPE for the
specified tasks.
• Ensure only qualified personnel install, operate, service, and maintain all electrical
equipment.
1. Check that the retrofitted EntelliGuard cassette has been completely racked into the cabinet.
2. Slide the bracket back into position as shown in the image below (
Figure 24)
and line up the holes
previously drilled with the holes on the locking bracket (
Figure 25).