10 Acceptance Testing

Introduction

The Galaxy Millennium Controller is tested before it leaves the factory, but many users
wish to add some test procedures as part of installation and turn-up. The tests
described here will simulate various alarm conditions and verify that the controller
functions properly. Follow the steps listed below in the order they are given.

Tools and Test Equipment

Tools and Test Equipment Required for Acceptance Testing

Digital Voltmeter (DVM) with dc accuracy of at least 0.05%
Short length of wire or clip lead for jumper
Jeweler’s screwdriver

Test Precautions

Follow these steps to test plant alarms when installing the Galaxy Millennium
Controller in a new plant. In a new installation, begin the sequence with the rectifiers
running with a dummy load on the plant bus bar.

For these tests, it is assumed that:

All rectifiers are functioning properly.

Plant batteries have received their original charges and are ready to support a
load.


If you are testing a controller in a live plant:

Some tests will cause a battery discharge. Insure that plant batteries are
capable of supporting the load.

Alarms will be generated. Notify the appropriate alarm monitoring personnel.