2–10

EPM 1500 SUB-METER – INSTRUCTION MANUAL

CHAPTER 2: INSTALLATION

Z

Take the black, red, blue and white (if available) #12 AWG feeder
phase tap wires and run them to

⇔A, ⇔B, ⇔C, and N (if available)

respectively (see Internal Fuse Block on page 2–11).

Z

Plug the fuse block into the meter head and hang the meter head
on the back box.

Z

Close up the breaker panel until the certification inspector arrives.