9 orion 3a manifold - valve adjustment procedure, Orion 3a manifold - valve adjustment procedure, Section 4.2.9 – Condec UPS3210 User Manual

Page 39

Advertising
background image

Maintenance & Service

35

4.2.9

ORION 3A Manifold - Valve Adjustment Procedure

For UPS3110 5000 PSI and above Models.

ORION 3A: Refer to “ORION 3A Valve Assembly Parts List” on page 47 and Figure 4-2 on the second foldout
11 x 17 sheet.

Tools required:

Hex wrench (.050")
Hex wrench (.061")
Snoop, leak gas detector (PN 64781)

NOTES: 1. * denotes reference to Figure 2-2 on page 5.

2. Customer must supply, as a minimum, input supply pressure with a supply gauge and pressure regulator.

1. Turn the supply pressure regulator off and vent manifold.

2. If not already done, remove the ORION

INPUT

and

VENT

Valve (outer) knobs (3) using the .061" hex

wrench.

3. Energize the unit and let warm up. Turn

RANGE SELECT

(*6) to highest range. To adjust

INPUT

Valve, go

to step 4.

4. Check to see that each knob insert (4) is securely fastened to the ORION input and vent valve shaft (11).

If it is loose, re-tighten the set screws (23) with the .061" hex wrench.

5. Using a .050" hex wrench, loosen the set screw (34) on each ORION input and vent valve locknut (2)

and turn each locknut clockwise to its stop.

6. Close the

INPUT

Valve by turning the Knob Insert (4) clockwise. until you feel the valve needle seat on

the O-ring (valve is now in closed position).

7. Rotate gears (6) on both Isolation valves, counter-clockwise until they stop, then rotate clockwise 1/2

turn (opening isolation valves).

8. Turn the supply pressure regulator to increase the supply pressure to between 80% and 100% of Full

Scale.

9. GAGE Model: Open the

VENT

Valve (*12) to atmosphere (rotate counter-clockwise), zero the indicator,

by momentarily pressing

ZERO

switch (*1), then close the

VENT

Valve (*12).

ABSOLUTE Model: Open the

VENT

Valve (*12) to atmosphere (rotate counter-clockwise), to release

line pressure, then close the

VENT

Valve (*12).

10. Slowly open the

INPUT

Valve by turning the Knob Insert (4) counter-clockwise until you notice the

displayed pressure increase. Then turn the Knob Insert slightly clockwise until the pressure stops rising.

11. Mark a radial line at the 12 o’clock position on the Knob Insert.

12. Turn the Knob Insert (4) clockwise to move the mark to the 6 o’clock position.

13. Turn the Locknut (2) counter-clockwise until it contacts the bottom of the stop washer (33). Tighten the

Set Screw (34) on the Locknut with the .050" hex wrench.

14. Install the

INPUT

Valve Knob (3) on the Knob Insert (4) and engage its Gear (5) with the smaller Isolation

Valve Gear (6). Turn the knob clockwise until the Isolation Valve is slightly snug.

CAUTION: DO NOT USE EXCESSIVE TORQUE WHEN DOING THIS, AS THE SEAT MAY BE DAMAGED

15. Remove the

INPUT

Valve Knob. Align the Set Screws (25) with the indentations on the Knob Insert.

Install the Knob on the Knob Insert while engaging the Knob Gear (5) with the Isolation Valve Gear (6).

16. Tighten the Set Screws (25) with the .061" hex wrench. The

INPUT

Valve is now adjusted.

17. To adjust the

VENT

Valve, follow steps 4 and 5.

18. Close the

INPUT

Valve by turning the Input knob (*10) clockwise.

19. Close the Vent Valve Knob Insert (4) clockwise until slightly snug.
20. With the supply pressure at 100% of Full Scale, open the

INPUT

Valve until the indicated pressure

stabilizes and then close the

INPUT

Valve.

21. Slowly turn the Vent Valve Knob Insert (4) counter-clockwise until the display starts to decrease, then

turn the Knob Insert (4) slightly clockwise until the indicated pressure stops decreasing.

22. Follow steps 11 through 15 replacing the term

INPUT

Valve with

VENT

Valve. The

VENT

Valve is now

adjusted.