Size the gas pipe appropriately to supply the necessary volume of gas required
for the T-M32 (240,000 BTU/H for Natural Gas or 240,000 BTU/H for Liquid
Propane) using ANSI233.1/NAPA 54 in the USA or CAN/CSA B149.1 in Canada
or local codes. Otherwise, flow capabilities and output temperatures will be
limited.

1. Install a manual gas shut-off valve between the T-M32 and the gas supply line.
2. When the gas connections are completed, it is necessary to perform a gas leak test either

by applying soapy water to all gas fittings and observing for bubbles or by using a gas leak
detection device.

3. Always purge the gas line of any debris and/or water before connecting to the gas inlet.

Natural Gas Supply Piping

Maximum Delivery Capacity of Cubic Feet of Gas per Hour of IPS Pipe Carrying Natural Gas of 0.60 Specific Gravity
Based on Pressure Drop of 0.5” WC

Based on Energy Content of 1000 BTU/Cubic Ft.: T-M32 requires 240 Cubic Ft./hr. Unit: Cubic Feet per Hour

Length of Pipe

Pipe

Size

10' 20' 30' 40' 50' 60' 70' 80' 90' 100'

125'

150'

200'

¾”

363 249 200 171

152

138

127

118

111 104 93 84 72

1”

684 470 377 323

286

259

239

222

208 197 174

158

135

1 ¼”

1404 965 775 663

588

532

490

456

428 404 358

324

278

1 ½”

2103 1445 1161 993

880

798

734

683

641 605 536

486

416

2”

4050 2784 2235 1913

1696

1536

1413

1315

1234 1165 1033

936

801

2 ½”

6455 4437 3563 3049

2703

2449

2253

2096

1966 1857 1646

1492

1277

3”

11412 7843 6299 5391

4778

4329

3983

3705

3476 3284 2910

2637

2257

Propane (LP) Gas Supply Piping

Maximum Capacity of Propane (LP) Gas Based on 11” WC supply pressure at a 1.0” WC pressure drop

Unit: kBTU per Hour

Pipe Size

Length in Feet

inches

10’ 20’ 30’ 40’ 50’ 60’ 70’ 80’ 90’ 100’

125’

150’

200’

¾”

567 393 315 267

237

217

196

185

173 162 146

132

112

1”

1071 732 590 504

448

409

378

346

322 307 275

252

213

1 ¼”

2205

1496

1212

1039

913

834

771

724

677 630 567

511

440

1 ½”

3307 2299 1858 1559

1417

1275

1181

1086

1023 976 866

787

675

2”

6221 4331 3465 2992

2646

2394

2205

2047

1921 1811 1606

1496

1260














10’ Length

3/4” Pipe Size

Gas Sizing Example

(Natural Gas)

15’ Length

1/2” Pipe Size

10’ Length

1/2” Pipe Size

Furnace

120,000BTU

10’ Length

1” Pipe Size

T-M32


240,000BTU

5’ Length

1-1/4” Pipe Size

Range

65,000BTU

10’ Length

3/4” Pipe Size

Dryer

35,000BTU

15’ Length

3/4” Pipe Size

5’ Length

1-1/4” Pipe Size

Gas Meter

B

A

Based on Energy Content of 1000BTU/Cubic Ft:

Divide each appliance’s BTU requirement by 1000BTU to get
the appliances Cubic Ft. requirement.

Takagi into account the distance the appliance is from the gas
meter, look in the above gas chart to properly size the line.

For sections of the gas line supplying gas to more than one
appliance (Ex: Point A to Point B), add up the cubic ft.
requirements of the appliances that are being supplied by that
section, and size to the farthest appliance.

For Example: The section from A to B supplies gas to the
furnace, range, and dryer. Adding up the BTU requirements and
dividing by 1000 yields a cubic ft. requirement of 220 cubic ft. of
gas. The farthest appliance is the range, which is 50 ft. away
from the meter. Looking at the above chart, and under the
column of 50ft., Section A to B needs to be 1” in order to supply
220 cubic ft.

Advertising