Scheduling Background Tasks

www.3ware.com

79

3

In the Schedule Rebuild Tasks section, select the appropriate setting:

Follow Schedule

or

Ignore Schedule

.

The illustration below shows this setting for the rebuild task schedule.

Removing a Task Schedule

By default, daily task schedules are defined, each starting at 12:00 am and
running for 24 hours.

A maximum of seven schedules can be defined. When seven schedules are
shown for any of the tasks, you must remove a schedule before you can add
another.

To remove a task schedule

1

Choose

Management > Schedule

from the menu bar.

The Scheduling page appears, showing the schedule for Rebuild/Migrate
Tasks.

2

To view Verify Tasks or Self-test Tasks, select it from the drop-down list
at the top of the page.

3

Select the checkbox next to the schedule(s) you want to remove.

4

Click the

Remove Checked

button.

The page refreshes, and the selected schedule(s) are removed. You can
now add another schedule.

Adding a New Task Schedule Slot

When you add a rebuild/migrate or verify task schedule, you specify the day
of the week, time, and duration for the task. For self-test schedules, you
specify day and time, but not duration. (Duration is not required for self-tests.)

Depending on the schedule and system workload, background tasks may
require more than one scheduled duration to complete.

Note:

Self-test schedules cannot be turned off in this way. To disable self-tests you

must either remove all schedule times, or uncheck the tests listed in the

Tasks

column. For more information, see “Selecting Self-tests to be Performed” on
page 80

.