Figure 8 – ADC ACE-142S/142V User Manual

Page 22

Advertising
background image

ADCP-96-015 • Issue 1 • July 2004

Page 16
© 2004, ADC Telecommunications, Inc.

Figure 8. Constructing the Concrete Pad for the ACE-142S/142V Cabinet

6 IN.

(15.2 CM)

4 IN. MIN.
(10.2 CM)

COMPACTED SOIL

SAND OR

GRAVEL

19616-A

TOP OF PMF SHOULD

BE FLUSH WITH TOP

OF CONCRETE

90 BEND

IN DUCT

TOPSOIL OR

DECORATIVE ROCK

GRADE

72.0 IN.

(182.9 CM)

9.0 IN.

(22.9 CM)

28.0 IN.

(71.1 CM)

26.1 IN.

(66.4 CM)

30.6 IN.

(77.7 CM)

44.0 IN.

(111.8 CM)

33.0 IN.

(83.8 CM)

REINFORCED

CONCRETE PAD

4 IN DUCT FOR

DISTRIBUTION CABLES

(LOCATE 1 - 2 INCHES

BELOW TOP OF PAD)

PAD MOUNT FRAME

CAST IN PLACE

4 IN DUCT FOR

FEEDER CABLES

(LOCATE 1 - 2 INCHES

BELOW TOP OF PAD)

DO NOT POUR CONCRETE INSIDE

THE PAD MOUNT FRAME

GROUNDING ROD

(LOCATE 1 - 2 INCHES

BELOW TOP OF PAD)

FRONT

Advertising