6. Cut both the splitter input fibers and the feeder cable fiber subunit at the cut length mark.

Make sure that the splitter input fibers and the feeder cable fiber subunit are of equal
length and the overall length is within the range specified.

7. Starting at the cut end, measure backward and mark the break-out lengths for the feeder

cable fibers and the splitter input fibers.

8. Starting at the breakout mark, remove the protective jackets to expose the feeder cable

fibers (may be stranded or ribbon fibers) and the splitter input fibers.

9. Install the splitter input fibers and the feeder cable fibers in the splice tray and complete all

splices per local practice. Refer to

Section 7

for information on how to use the round

splice trays and then return to Step 10 to continue this procedure.

10. After splicing is completed, the splice tray cover replaced, and the excess slack rolled up,

insert the splice tray into the designated mounting slot.

11. Repeat this procedure for each feeder cable fiber subunit.

12. Designation labels, shown in

Figure 18

and

Figure 19

, are provided on the front door of

the cabinet for recording splitter module information. For each splitter, indicate the splice
tray number, feeder cable fiber number, splitter module number, and service information.

Figure 18. Splitter Module Designation Label - Type 1

19629-A

SPLITTER

MODULES

12

11

10

9

8

7

6

5

4

3

2

1

SPLITTER MODULE LABEL

FRONT DOOR