Connecting the dc power and the motor power cables – ElmoMC ExtrIQ Gold Line Servo Drives-Gold Eagle User Manual

Page 26

Advertising
background image

Gold Eagle Installation Guide

MAN-G-EAGIG-EC (Ver. 1.000)

||Connecting the DC Power and the Motor Power Cables|

www.elmomc.com

26

Table of Contents

9.5. Connecting the DC Power and the Motor Power Cables

This section describes the installation of the cable terminal lugs for both the Main Power Cables to
VP+, VN-, and PE terminals on the Gold Eagle, and the Motor Power cables to the M1, M2, M3, and
PE terminals on the Gold Eagle.

Cable Connections

Table 2: Connecting the PE Cables

1.

Connect the appropriate terminal lugs from the DC Power Input cables to the VP+, VN-, and
PE terminals on the Gold Eagle as shown in Table 2.

2.

Connect the appropriate terminal lugs from the Motor Power cables to the M1, M2, M3, and
PE terminals on the Gold Eagle.
a.

Install the motor cable to the drive using a barrel connector, M6 spring washer, and
secure with anM6 nut (to the drive). The required M6 nut torque is 3 Nm.

b.

Install the PE wire to the drive, using a barrel connector, M5 flat washer, M5 spring
washer, and secure with an M5 screw to the heat-sink. The required M5 screw torque
is 3 Nm.

The phase connection could be arbitrary as Elmo Application Studio (EASII) will establish the proper
commutation automatically during setup. When tuning a number of drives, you can copy the setup
file to the other drives and thus avoid tuning each drive separately. In this case the motor-phase
order must be the same as on the first drive.

Advertising