Post installation (testing) – Rockwell Automation 1500 Modular Protection System Conversion Kit (Bulletin 1406 to Bulletin 825 Plus) User Manual

Page 22

Advertising
background image

1500-IN058D-EN-E – June 2013

4-10

Installation

Post Installation (Testing)

Failure to follow these steps can result in damage to
equipment and/or personal injury.

1. Inspect the interior of the enclosure for contamination, loose bolts,

tools or metal chips, and vacuum clean if necessary.

2. Account for all the tools used. If a tool or hardware is unaccounted

for, do not energize the equipment.

3. Inspect the wiring and the control scheme to ensure proper

operation. Extra care should be taken when inspecting the
connections for the current transformer and ground fault circuits, to
ensure neither circuit is open or short-circuited during power-up.

4. For medium voltage controllers, follow items 5 though 7. For other

styles of controllers, the intent of this section is to apply control
voltage to the controller circuit, including the 825 Plus.

5. The isolation switch must be in the fully opened position (the

isolation switch handle moved to the OFF/down position).

6. Connect a remote 120VAC external power source to the

‘NORMAL-OFF-TEST’ (N-O-T) switch assembly test receptacle
located in the low voltage compartment. (Figure 4.24 )

7. Turn the N-O-T selector switch to the TEST position. (Figure

4.25)

With the selector switch in the test position, power
will be applied to the control circuit. Additional
caution must be taken to prevent accidental contact
with the 120VAC.

Figure 4.24

Figure 4.25

A T T E N T I O N

A T T E N T I O N

I M P O R T A N T

I M P O R T A N T

Advertising