Figure 13: Wiring Diagram,  Volt Standing Pilot with Continuous or Gravity Circulation

SEQUENCE OF OPERATION
NORMAL OPERATION

1. When the thermostat call for heat, the vent damper

will open (see paragraphs 17A through 17D). The

gas valve is energized allowing main gas to flow and

operation of the main burners.

2. Where condensation of flue gas is encountered in

boiler flues a reverse acting circulator control should

be installed to stop the circulator before the boiler

water temperature drops to that which flue gas

condensation may occur.

3. After the thermostat is satisfied the main valve will

close and main burner flames will be extinguished.

The vent damper will close (see paragraph 17E). If

the boiler is so equipped, circulator will continue to

run.

SAFETY ShUTDOWN

1. high Limit Switch: In the event excessive boiler

water temperature is developed the high limit switch

will open interrupting power to the gas valve. The

main burners will be extinguished immediately.

Normal operation will be resumed when the boiler

water temperature drops to a point where the high

limit switch closes.

2. Blocked vent Switch: In the event excessive

blockage in the vent system is developed the

blocked vent switch will open interrupting power to

the gas valve. The main burners will be extinguished

immediately and the vent damper will remain open

until the thermostat is turned off. The source of

blockage must be corrected by trained and skilled

personnel from a qualified service agency before

resetting switch.

3. Flame Rollout Switch: In the event excessive

blockage in the boiler section flue passageways is

developed the flame rollout switch will open

interrupting power to the gas valve. The main

burners will be extinguished immediately and the

vent damper will remain open until the thermostat is

turned off. If the flame rollout switch is activated do

not attempt to place the boiler in operation. The

source of the blockage must be corrected and the

flame rollout switch replaced by trained and skilled

personnel from a qualified service agency.

4. Pilot: The thermocouple proves pilot flame and in

the absence of such within 45-90 seconds causes the

combination gas valve, which is equipped with a

100% shut-off provision, to be de-energized, thus,

preventing main gas or pilot gas flow.