TO R Q U E M O D U L E I N S T A L L A T I O N

Load Cell Installation

Version 4

Torque Module Installation and User Guide for Model 250 Dynamometers

1-9

4

Route the load cell cable.
4a

Make sure the load cell cable is clear of any power cables or hot or rotating
objects.

4b

Secure the load cell cable to the three existing bolts underneath the
aluminum top using three 5/8-inch cable clamps and 1/4-inch lock nuts.

Figure 1-10: Secure the Load Cell Cable to the Dyno

4c

Remove the bolt on the brake and place a 3/8-inch cable clamp on the bolt.

4d

Run the load cell cable through the clamp and tighten the bolt.

Figure 1-11: Secure the Load Cell Cable to the Brake

secure under aluminum top

load cell cable

load cell

cable

cable clamp

load cell cable