5 Putting into operation

22

Melting Point M-565 Operation Manual, Version D

Accessories

• Place the melting point capillaries in the hole of the housing. The second hole is a reservoir for

used capillaries.

5 .2 .2

Connecting to a PC with MeltingPoint Monitor software

The Melting Point M-565 can be operated
in connection with the MeltingPoint Monitor
software. In this case, connect the instrument
with the PC or laptop using the USB cable. For
detailed information check installation guide on
software CD.

a Melting Point M-565
b Laptop or PC with MeltingPoint Monitor

software

Fig. 5.1: Connection of Melting Point M-565 with the MeltingPoint Monitor software.

5 .2 .3

Power connection

ATTENTION
Make sure that the voltage of the socket corresponds to the voltage given on the type plate of the
instrument. Ensure that the instrument is grounded. External connections and extension cables must
be provided with a grounded conductor lead (3-pole couplings, cable, or plug equipment) as the
mains lead has a molded plug to avoid risks due to inadvertently defective wiring. Make sure that no
electric sparks form in the instrument or its surroundings as they might damage the instrument. Make
sure that the mains connector is freely accessable at any time.

5 .2 .4

Calibration

NOTE
Before use it is recommended to calibrate the apparatus. Use supplied calibration substances only.

Calibration is carried out in accordance with section 6.4 of these operating instructions.

Advertising