3.9.1 Natural Gas Connections

Natural Gas Piping Sizes

3.9.1.1

Contact your local gas supplier for natural gas pipe sizes and meter types.

Natural Gas Piping Connections

3.9.1.2
The boiler gas pipe is equipped with external 3’’ ASME B16.5 flange, onto which the tail

piece of the gas shut off valve can be connected. Use appropriate sealing.
The connection to the boiler must include a suitable method of disconnection and a gas

control valve must be installed adjacent to the boiler for isolation purposes.

Natural Gas Supply Pressure Requirements

3.9.1.3
The nominal inlet working gas pressure measured at the boiler should be 7” W.C. (18 mbar)

for natural gas. Maximum pressure with no flow (lockup) or with the boiler running is 10.5

inches W.C. Minimum pressure with gas flowing (verify during boiler startup) is 4.0 inches

W.C.

3.9.2 Propane Gas Connections

Propane Gas Piping Sizes

3.9.2.1

Contact your local gas supplier for Propane gas pipe sizes, tanks, and 100% lockup gas
pressure regulator.

Propane Gas Piping Connections

3.9.2.2
The boiler pipe is provided with external 3’’ ASME B16.5 flange, onto which the tail piece of

the gas shut off valve can be screwed. Use appropriate sealing.

The connection to the boiler must include a suitable method of disconnection. Use a gas shut

off valve compatible with propane gases. A sediment trap must be provide upstream of the

gas controls.

Propane Gas Supply Pressure Requirements

3.9.2.3

Pressures required at gas valve inlet pressure port:

Nominal gas pressure is

11 inches W.C.

Maximum gas pressure is

13 inches W.C. with no flow (lockup) or with boiler running.

Minimum gas pressure is

8 inches W.C. with gas flowing (verify during boiler startup).

NOTE

Ensure that the high gas pressure regulator is installed at least 6 to

10 feet upstream of the boiler.