CIRCUTOR CBS8 (Available until stocks) User Manual

Page 16

Advertising
background image

----- Relay Station CBS-8 -------- --- Page No. 15

4.2.- Test mode

This is used to check the operation of toroid – CBS-8 connection, operational

relays, the equipment’s electronics and the LEDs.

The equipment does not check the line whilst it is

testing

Pressing the “TEST” button for three seconds will enter this mode when the

equipment is in normal operating mode.

The test is: injecting a current via the test terminals on the transformer. This

current is detected by the selected CBS-8 channel as an earth leakage, tripping it
operational relay.

The results of the test of the connection between transformer and the relay

station is shown by different messages on the screen:

Working correctly

Working incorrectly

)

Channel to be tested

)

Test result

If no button is pressed for 30 seconds the equipment automatically

goes into normal mode without reconnecting any blocked relay

Advertising