Installation Of Vertical Vent DV

Vertical Terminations must be installed:

minimum 2' (two feet) above the highest point where

vent passes through the roof.

minimum 6' (six feet) from a mechanical air inlet

minimum 18" (1 1/2 feet) from a parapet wall.

Maximum vent height is 30 feet above fireplace.

Note: Flame characteristics will change if the maximum vent

height is used.

Minimum clearance to combustible construction around the

vent pipe is 1" on all sides must be maintained, except on hori-

zontal venting where the

top of the pipe must have a clearance of

at least 2".

A maximum of two offsets

(each offset has two 90° bends) may be

made if the length of the offsets does not exceed 25% of the vertical
vent height, when measured center to center of piping.

Example:

Typical vent installation.

30' vertical vent

2 - 2' offsets required

25% of 30' = 7-1/2' max. offset allowed

This venting configuration meets requirements.

A - Termination

PVTK-1

B - Flex sections

PFL-1 (12" section)

PFL-2 (24" section)

PFL-3 (36" section)

PFL-4 (48" section)

C - Solid sections

PEXT-1 (12" section)

PEXT-2 (24" section)

PEXT-3 (36" section)

PEXT-4 (48" section)

D - Support Ring & Plate

PSPXT-7 (8" dia.)

E - Firestop

PS-8 (8" dia.)

F - Roof Flashing

PRF-7 (1/12 - 7/12 pitch)

PRF-12 (7/12 - 12/12 pt.)

Figure 18. Vertical venting using 2 offsets (1 offset= two 90° bends).

* If reducing to 4"/7" venting see figure 19.

Figure 17. Vertical venting using 1 offset (1 offset= two 90° bends).

* If reducing to 4"/7" venting see figure 19.

Figure 16. Straight, vertical venting.

* If reducing to 4"/7" venting see figure 19.

Top Vent

Advertising
This manual is related to the following products: