Three phase ups systems 8.0 help – OnLine Power Battery Backup System User Manual

Page 68

Advertising
background image

OLP

Three Phase UPS Systems

8.0

HELP

8-3

Abnormal

Description & Checkpoint

Solution

The fuses positioned behind PCB
holder have been blown or are not
installed properly.

Replace the fuses or
install them properly.

(6) Fans do

not work
while UPS is
on.

Abnormal voltage output in R phase.

Refer to PCB LED
Detecting Guide and
check the 3T PCB of R
phase.

Voltage limit function failure in the
3B, which contributes to the DC
voltage, goes over 430V.

Refer to PCB LED
Detecting Guide and
check the 3B PCB.

(7) The
rectifier shunt
down and
HIGH DC
LED is lit.

3C PCB has problem.

Refer to PCB LED
Detecting Guide and
check the 3C PCB.

RESERVE AC FAIL LED lights up.
LCD menu also displays the abnormal
voltage in reserve. (REAL TIME

DATA menu → RESERVE DATA
menu).

Check the reserve wiring
and connect with the
correct source.

Fuse has blown in 3A PCB

Replace the fuse.

(8) Abnormal

voltage in
reserve.

If the abnormality cannot be corrected
after the solution actions have been
taken.

Refer to PCB LED
Detecting Guide and
check the 3A PCB.

RESERVE FREQ FAIL LED lights up.
LCD menu also displays the abnormal
voltage in reserve. (REAL TIME

DATA menu → RESERVE DATA
menu).

Check the reserve wiring
and connect with the
correct source.

Fuse has blown in 3A PCB

Replace the fuse.

(9) Abnormal

frequency in
reserve.

If the abnormal cannot be corrected
after the solution actions have been
taken.

Refer to PCB LED
Detecting Guide and
check the 3A PCB.