Output Cable Installation - Phase Stabilizer 15 - 100 kVA and Constant Power 18

The customer-furnished output power cable provides power from the unit to a connected load or to a Power
Island when distribution to more than one connected load is required.
This cable should be installed through the right side panel. No holes are provided in the panel. A hole can be
sized, located and drilled or punched when the cable is installed.

Procedure

1.

Turn OFF facility circuit breaker, lock and tagout according to OSHA requirements.

2. Open

front

door.

3.

Verify that the Main Input Circuit Breaker is set to OFF (as applicable).

4.

Open the top panel by removing the screw from the front panel and lift the top panel to it’s up position.

5.

Remove rear panel by unbolting 6 screws located on the corners and right and left sides of the panel.

DANGER!!

VERIFY THAT INCOMING HIGH-VOLTAGE CIRCUITS ARE DE-ENERGIZED
BEFORE CONTINUING WITH THIS PROCEDURE.

6.

Punch or drill holes in right side panel to accomodate output cable.

7.

Route and connect the 4 power wires to output terminals. (X0, X1, X2, and X3)
See Illustration 1-6.

8.

Route and connect the ground wire to the ground lug on the cabinet.

9.

Proceed to Section 3-1-7, Startup to complete the installation.