OnLine Power

6002-032 REV H

4-13

4-7-4 Output Interconnect Cable Installation (continued)

10. Access the interior of Power Conditioner or Voltage Regulator as follows:

• Constant Power 18 and Phase Stabilizer (15 - 75 kVA)

a. Raise hinged lid.

b. The Power Island Interconnect cable can be routed through the bottom or through the right side of the CP

18 or Phase Stabilizer.

• Power-Reg, Ultra-Reg, Phase Stabilizer (100 - 400 kVA)

a. Remove top cover by unbolting two bolts on each side of cover.

b. Remove front panel by unbolting six bolts.

11. Route Output Interconnect Cable up through floor opening (as applicable) and into conduit entry opening.

12. Connect the grounding conductor to the ground bus in the Power Conditioner or Voltage Regulator.

13. Connect the power conductors to the Output Power Terminal Block in the Power Conditioner or Voltage

Regulator.

4-7-5 Output Cable Installation
The following instructions cover installation of the Output Cables between the connected loads and the Power
Island:

Note

The equipment to be connected to the Power Island may require special grounding procedures.
Refer to technical documentation which accompanies that equipment.

Procedure

1.

Turn OFF facility circuit breaker to power conditioner or voltage regulator, lock and tagout according to
OSHA requirements.

2.

Open front door of Power Island.

3.

Verify that IMCB is set to OFF.

4.

Verify that all output circuit breakers are set to OFF.