Installation process – Sanyo CM1972 User Manual

Page 77

Advertising
background image

15

3. Installation Process

3-1.

Embedding the Tubing and Wiring

Do not connect tubes to locations that are embedded.

Be sure to bind refrigerant tubing and inter-unit cables

together with vinyl tape.

The power cable must be obtained on-site.

(#12: Less than 85 ft.)

# ... AWG (American Wire Gauge)

Be sure to apply the provided labels to both ends of

the inter-unit cables to prevent miswiring.

Securely seal the end of embedded tubing with vinyl

tape in order to prevent dirt or moisture entry.

In order to prevent insulation breakdown and ground

faults, do not allow the wire ends to contact rainwater,

or be subject to dew condensation.

Deburring

Before

After

Fig. 8

3-2. Use of the Flaring Method

Many of the conventional split system air conditioners

employ the flaring method to connect refrigerant tubes

which run between indoor and outdoor units. In this

method, the copper tubes are flared at each end and

connected with flare nuts.

3-3. Flaring Procedure with a Flare Tool

(1) Cut the copper tube to the required length with a

tube cutter. It is recommended to cut approx. 12" to

20" (30 to 50 cm) longer than the tubing length you

estimate.

(2) Remove burrs at the end of the copper tube with a

tube reamer or file. This process is important and

should be done carefully to make a good flare.

(Fig. 8)

07-156 CM-CLM1972-3172 6/6/07 9:35 AM Page 15