Service Manual 77

2-way, 3-way Valve

(1) Pumping down

Procedure

1. Confirm that both the gas side and liquid side

valves are set to the open position.

- Remove the valve stem caps and confirm that the

valve stems are in the raised position.

- Be sure to use a hexagonal wrench to operate

the valve stems.

2. Operate the unit for 10 to 15 minutes.

3. Stop operation and wait for 3 minutes, then con-

nect the manifold gauge to the service port of the
gas side valve.

- Connect the hose of the gauge with the push pin

to the service port.

4. Air purging of the charge hose.

- Open the Low-handle valve on the gauge

slightly to air purge from the hose.

5. Set the liquid side valve to the closed position.

6. Operate the air conditioner at the cooling cycle

and stop it when the gauge indicates 1kg/cm

2

g.

7. Immediately set the gas side valve to the closed

position.

- Do this quickly so that the gauge ends up indicat-

ing 1kg/

g.

8. Disconnect the charge set, and mount the liquid

side and gas side valve caps and the service port
nut.

- Use torque wrench to tighten the service port nut

to a torque of 1.8kg.m.(4.2kg.m/5.5kg.m)

- Be sure to check for gas leakage.

Indoor unit

Outdoor unit

Liquid side

Close

Gas side

2-Way

valve

Open

3-Way

valve

manifold gauge

Indoor unit

Liquid side

Close

Gas side

2-Way

valve

Open

3-Way

valve

Hi- handle

(CLOSE)

Low-

handle

(CLOSE)

• Be sure to short pressure S/W. otherwise Low pressure S/W detect low pressure skete and stops the compressor.