6. Installation

PNEG-1095 FCDL 4.00" Corrugation Externally Stiffened Grain Bin

67

Locating Chutes

1. Starting from the first row of holes in the top

sheet, measure down the “starting distance”
for the bin.

See Sidedraw Chute Chart on

Page 65

.

(See Figure 6V on Page 65

and

See Figure 6Y.)

2. Keep adding the required number of chutes,

making sure to leave 8" between the chute bolt
holes.

(See Figure 6V on Page 65.)

Locating Discharge Opening

1. The last bolt hole in the chute should line up

with the center of the discharge chute opening
that is to be cut.

(See Figure 6Z.)

Therefore,

you should be able to approximate an opening
by measuring 9-1/2" above and below the
last bolt hole of the chute. Mark horizontal
cut lines.

2. To find the vertical center of the chute

opening, measure over 11" to the right and
left of the chute bolt rows. Mark center point.

(See Figure 6Z.)

Then from the center point,

measure 7" on both sides and mark vertical
cut lines.

3. Cut opening where marked, make sure

corners have a minimum of 1-1/2" radius.

(See Figure 6Z.)

Figure 6Y

Figure 6Z

Advertising