6. Installation
46
PNEG-1094 Farm Grain Bin - 4" Corrugation
24" Safety Cage Bell Sections
Attach the vertical supports to the hoop half assembly from the final safety cage installation using
5/16" x 3/4" bolts and nuts (with the heads on the inside of the cage). Assemble the special bell safety
cage hoop halves and attach to other end of vertical supports. The vertical support should be bent at the
flat area to allow for the bell section angle. Attach the safety cage brackets to the ladder as shown in
. Once the safety cage brackets are installed, attach the bell safety cage hoop half
assembly to the safety cage brackets and tighten bolts.
NOTE: The safety cage bell section is to be used at the point of termination of the safety cage and should
be just above the concrete (generally 7' to 8').
Figure 6T 24" Bell