Options for 2 ring doors, Auger hood – Grain Systems Tanks PNEG-1094 User Manual

Page 52

Advertising
background image

6. Installation

52

PNEG-1094 Farm Grain Bin - 4" Corrugation

Options for 2 Ring Doors

Auger Hood

Inner Door Auger Hood 12' (3.66 m) -
24' (7.32 m) Diameters Only

1. Remove bolts, lock washers and

nuts along each side of large
square opening on the inner
door panel.

2. Position auger shield as shown in

Figure 6X

and bolt to underside of

top angle with bolt heads under
shield. Replace bolts, lock
washers and nuts through inner
door panel and auger shield.

(See Figure 6X.)

3. Attach inner door panel to inner bin

door and outer door panel to the
outer bin door.

Bin Step

4. Attach the left and right sides to the

sides of the bin step using four (4)
5/16" x 3/4" grade 5 hex head bin
bolts and nuts.

(See Figure 6Y.)

5. Center assembled step under bin

door and use it as a template
to field drill the holes in the
side wall sheet on the ridges of
the corrugation.

Figure 6X

Figure 6Y

CAUTION

Improperly unloading grain through door opening may cause grain bin failure.
Unloading directly through the door opening should be limited to grain bins no
larger than 24' (7.32 m) diameter and grain depths no greater than 18' (5.49 m).
Unloading from the door opening should be done only with use of an auger hood
with the auger inserted through the opening all the way to the center of the bin.

Advertising