PNEG-1702 ETL Listed GSI/FFI Portable Dryer Manual

6. Competitor/Dri-Tek Test Firing

Before the dryer is filled, thoroughly inspect the unit and check the operation of the dryer as follows.

Inspect the Metering Rolls

Figure 6A 4" Meter Roll

Figure 6B 7" Meter Roll

Open all metering roll access doors and inspect each compartment for any bolts, nuts or other foreign
material, that may cause possible jamming of the metering rolls.

CAUTION

Before attempting to operate the dryer make sure all safety shields are in place, all
bottom clean-out and rear access doors are closed and all personnel are clear of
the dryer.