15. Install the top shaft or stub shaft and coupling.

Do not drop any foreign object into the

bowl assembly. Such an object can cause

serious damage to the pump and any downstream

components. Any foreign object dropped into the bowl

assembly must be retrieved prior to continuing assembly.

INSTALLING THE DISCHARGE HEAD
VIT Pumps are provided with either a cast iron or

fabricated steel type head. For pump with below

ground discharge, a motor stand is provided instead the

discharge head. Install the discharge head as follows:
1. If the stuffing box (See Fig. 9) or tension nut (See

Fig. 10) is assembled to the head, remove it and all

the attached piping.

2. For threaded column, check to be sure that the

column flange (637) is securely attached to the

bottom of the discharge head. Check and tighten

the capscrews (or socket head screw) gradually in

diametrically opposite pairs.

3. Remove coupling guard if provided. Attach a sling

to the lifting lugs on the side of the discharge head

through windows and hoist discharge head over the

protruding top shaft (or stub shaft).

Do not bump or scrape the shaft protrud-

ing above the column. This could result in

bending or damaging the shaft.
4. Orient the discharge head in the required position

and lower the head. Center the vertical hole with

the top shaft protruding above the column. For

threaded column, continue to lower the discharge

head until the large threaded hole in the bottom

of the discharge head rests squarely on top of

column. Clean the threads at upper end of column

assembly and lubricate with thread compound.

Rotate discharge head, screw it onto the column,

for short set-pump, (without the column adjusting

nipple) butting the top of column tightly against the

discharge head.

5. For flanged column, continue to lower the discharge

head until the discharge head engages the column

flange. Install capscrews and secure discharge head

to the column flange. Tighten capscrews gradually

in diametrically opposite pairs. Lift the pump

assembly high enough to allow rotation of the

supports. Realign and lower assembly. Install and

tighten remaining capscrews. Repeat the rotating

and the tightening procedure until all capscrews are

uniformly tight.

6. Hoist the discharge head by lifting lug and remove

the elevator clamp attached to column.

7. Remove the support timbers or I-beams and clean

the top of foundation or base plate. Orient the

discharge head in the required position.

NOTE: Sling should be rated to handle in excess of the

pump weight.

8. Lower bowl, column and head assembly, until

discharge head mounting flange engages base plate.

Secure discharge head to the foundation or base

plate. Check the levelness of the discharge head in

all directions, utilizing a machinist level across the

driver’s mounting surface of the discharge head.

9. Check whether the top shaft (or stub shaft) is in the

center of the stuffing box bore. If not, the shaft must

be centered by shimming the head base and the sub

base (or the foundation).

10. Rotate the shaft approximately 90º. Check again

whether the shaft is at the center of the stuffing box

bore or not. If not, either the top shaft is bent or the

first shaft below it did not butt properly. Correction

must be made before the installation procedures can

proceed.

INSTALLING THE STUFFING BOX
Assemble stuffing box as shown in Figure 9.
1. Clean the surface of the discharge head where

the stuffing box will be mounted and remove

any nicks or burrs with a fine flat file. Position

gasket on surface. Slide stuffing box (616) down

over headshaft and into position on the gasket.

Secure stuffing box with capscrews. Make sure

the capscrews are torqued equally to prevent

misalignment.

2. Grease the packing ring (620) for easier installation.
3. Twist the packing ring sideways to get it around the

shaft easily. Start the first ring into the stuffing box.

When the entire ring is worked in using the fingers,

tamp it down using a split wood bushing (or equal)

and push the packing ring down firmly. It must seal

on the shaft and bore of the stuffing box. Install all

three (3) rings in this manner. Stagger ring joints 90º

apart. The split gland may be used as a tamper for

the top ring.

4. Insert lantern ring (622) into stuffing box. Be sure

it is properly positioned so that it aligns with the

lubrication passage in the stuffing box.

5. Insert three (3) additional rings of packing. Stagger

ring joint 90º apart.

6. Install the split gland and screw nuts on the split

gland studs. Tighten nuts then relieve the nuts and

tighten finger tight.

Check that the split gland is square in the

stuffing box. Cocking can cause uneven

compression of packing and damage to the shaft or sleeve

and heat up the shaft and stuffing box.

CAUTION

CAUTION

CAUTION

Figure 9

(619) STUD (2)

(735) HEX NUT

(2)

PORT “A”

(624) BYPASS LINE

(618) GLAND

PORT “B”

(621) O-RING

(620) PACKING

(6 RING)

(616) STUFFING

BOX

(617) BEARING

(622) LANTERN

RING

Advertising