3.  Preparation for Installation

Read the safety instructions on page 4 before installing the UPS.

3.1  Inspection

Inspect the UPS upon receipt. Notify the carrier and dealer if there is any damage. The packaging is

recyclable; save it for reuse or dispose of it properly.

3.2  Storage

If stored at -15 to +30 °C (+5 to +86 °F), charge the UPS batteries every three months.
If stored at +30 to +40 °C (+86 to +104 °F), charge the UPS batteries every two months.

3.3  Unpacking

1. Remove the UPS from the packing materials.

2. A standard unit includes:

• One (1) user manual.
• One (1) AC input power cord (not supplied with hard wired models).
• Two (2) IEC output cables ( for UPS models with IEC sockets only).
• One (1) set of UPS communication software on CD with RS232 cable.
• The accessories shown below for tower and rack mounting: