Operation, Siemens lmv51 control, Operating points on the siemens lmv control – Fulton Vantage (VTG) Fully Condensing Hydronic Boiler User Manual

Page 42: Normal operation, Pre-ignition

Advertising
background image

© The Fulton Companies 2013

3-6

OPERATION

VTG-IOM-2013-0815

SECTION 3



ã

WARNING

Non-Fulton product information is for
reference purposes only. No Fulton
document should substitute for full
review of documentation available
from the component manufacturer.

This boiler is equipped with an
ignition device which automatically
lights the burner. Do not try to light
burner by hand.



Ð

CAUTION

Do NOT leave unit unattended in
Manual Operation, in this mode the
LMV51 will ignore its internal Set Point.

Siemens LMV51 Control

Operating Points on the Siemens LMV Control

Every Vantage boiler comes with a Test Fire Report from the factory. This includes
nine operating points that are set up in the Siemens LMV control by Fulton’s
technicians. Point #1 needs to be set up specifi c to job site operating conditions
when the boiler is set up and commissioned by a fi eld service technician:

For Natural Gas/Propane fi ring, Parameter MinLoad should be at 0 for units
that have a setpoint greater than 100°F (38°C).

Parameter MinLoad should be at 20 for units with a setpoint less than 100°F
(38°C).

If the boiler is operating on an outdoor reset schedule and the setpoint
falls below 100 F (38°C) at any time, Parameter MinLoad should be at 20.

Normal Operation

The Siemens LMV51 system is a fully packaged burner management system,
linkageless control and fi rst out annunciator. When operating the Siemens LMV
systems, all changes are made through the Siemens AZL display. The left and
right arrow keys are used for scrolling through the menu and changing controller
parameters. Enter accepts the menu and parameter changes. It is possible to
return to the main menu at any time by repeatedly pressing Escape. When
running the boiler, the status of the burner is to be monitored with the Siemens
AZL display. If at any time the burner control locks out on a fault condition and
the red fl ame failure light illuminates:

1. Read the diagnostic feedback on the AZL display, address the fault if

possible.

2. Press escape on the AZL once.

3. Press enter on the AZL to reset the control. The red light should go out.

4. If the fault persists contact Fulton.

If the boiler has a dual fuel burner, the burner setup procedures must be
performed for each fuel.

Pre-Ignition

Perform the following prior to ignition:

1. Verify the main burner position switch is in the OFF position. If the boiler

is dual fuel, verify the fuel selector switch is turned to the correct fuel
position.

2. Supply power to the boiler. The AZL will display “System Test” and then

move to the main menu.

3. Select PWLogin, press Enter. Select AccessServ. Press Enter. This type of