Run Tests

1. On the framework dialog, click Start to begin testing.

When tests are in progress, this button changes to Stop. Click it at any time to stop the
test in process. You’ll be able to resume from the point of termination or from the
beginning of the test.

2. Follow the pop-up window prompts. QualiPHY guides you step-by-step through each of

the tests described in the standard specification, including diagrams of the connection to
the DUT for each required test mode.

3. When all tests are successfully completed, both progress bars on the framework dialog

are completely green and the message “All tests completed successfully” appears. If
problems are encountered, you’ll be offered options to:

Retry the test from the latest established point defined in the script
Ignore and Continue with the next test
Abort Session