2 installation, 1 fix and connect the pyrometer, Fig. 8 – LumaSense Technologies IGA 740 User Manual

Page 20: Pyrometer connections

Advertising
background image



Starting Up

16

KLEIBER

740

6.2 Installation

6.2.1

Fix and connect the pyrometer

DANGER

There is danger of injury and possible equipment damage by connection of cables under
power!

Never connect cables under power! Make sure that the voltage supply is switched off before
connection of the cables to the pyrometer!


Install the pyrometer as follows:

1. Mount the pyrometer with the help of the retaining pin and taking into account the

conditions specified in section 6.1 for the intended place of use.

2. Connect, if necessary (only in case of ambient temperatures more than 40°C) the

water cooling (position 1, Fig. 8).

3. Connect the coloured wires of the 5-pole connecting cable (item B, Fig. 8) to

appropriate connections of a switchboard. For wire configuration please see legend
to fig. 8.

4. Connect the 5-pole connecting cable to the pyrometer at the back of the instrument

(item 2, Fig. 8) and to the power supply.

5. Double check stable set up of the pyrometer.

The pyrometer is ready for use and can be switched on.

Fig. 8

Pyrometer connections

1

Cooling circuit connections

2

Connect 5-pole connecting cable.

IMPORTANT

Operation of the pyrometer about ambient temperatures of more than 40°C is only
permitted with water cooling

! Connect the pyrometer to a suitable cooling circuit with

ordinary tap water! The use of coolants is permitted only with the agreement of the
manufacturer!

The temperature of the cooling water must lie between 10 °C and 35 °C. Condensation build-
up due to the low temperature of the cooling water is to be avoided.

Advertising