Installation

NOTICE:It is assumed that the installer who grouts the baseplate has knowledge of acceptable
methods. More detailed procedures are described in various publications, including API
Standard 610, 8th Edition, Appendix L; API RP 686, Chapter 5; and other industry standards.

1. Clean all the areas of the baseplate that will come into contact with the grout.
2. Build a dam around the foundation.
3. Thoroughly wet the foundation that will come into contact with the grout.
4. Pour grout through the grout hole into the baseplate up to the level of the dam.

When you pour the grout, remove air bubbles from it by using one of these methods:

• Puddle with a vibrator.

• Pump the grout into place.

5. Allow the grout to set.

1. Baseplate
2. Shims or wedges
3. Grout
4. Foundation
5. Sleeve
6. Dam
7. Bolt

6. Fill the remainder of the baseplate with grout, and allow the grout to set for at least 48

hours.

1. Baseplate
2. Grout
3. Foundation
4. Dam
5. Bolt

7. Remove the leveling jackscrews after the grout hardens in order to remove any stress

points.

8. Tighten the foundation bolts.
9. Recheck the alignment.

Model 7200CB, API Type BB5 Barrel Multistage / ISO 13709 2nd Edition / API 610 11th Edition Installation, Operation, and

27