Bosch 25/32kW User Manual

Page 31

Advertising
background image

FILLING THE SYSTEM

INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER GREENSTAR HEATSLAVE EXTERNAL 12/18-18/25-25/32
8 716 113 389b (09/07)

30

C

O

MMI

S

S

IO

N

IN

G

1

Pull lever (C) up and push to the left to

move the diverter valve to the mid-position
between ports A and B.

Push and hold lever (C) down to lock.

2

Loosen the automatic air vent cover.

4

Sealed systems only; check and if required,

adjust the expansion vessel pressure using
the Schraeder type valve (D).

The charge pressure of the built-in 12 Litre
expansion vessel is 0.5 bar as dispatched,
which is equivalent to a static head of 5
metres (16.7 ft).

If an extra expansion vessel is fitted to the
central heating return, adjust this to the same
pressure as the appliance internal expansion
vessel, refer to separate instructions supplied
with the extra expansion vessel.

4

Open all system and radiator valves (E).

Turn on the water main stop cock.

Open vented systems only; turn on the

water to the system feed and expansion

cistern and allow the system to fill.

Sealed systems only; fill the system to

between 1 and 2 bar pressure via a WRAS
approved filling link. Monitor the pressure

gauge during venting and repressurise if

required.

Check air is being discharged from the

automatic air vent.

Vent all radiators, retighten when completed,

check the system and correct any leaks.

Bleed air from both of the secondary heat

exchanger air vents (F).

Bleed air from the pipework using the

pump bleed screw.

5

Sealed systems only; connect a suitable

hose to the Heatslave tank drain. Open the
drain valve to reduce the system to the

correct pressure, then close the drain valve.

Ensure safe disposal of the discharge.
Rotate the adjustable pointer on the
pressure gauge to record the set system

pressure.

6

Check system and rectify any leaks.

Push lever (C) to the left and pull

upwards to allow the lever to return to

position A.

Leave the lever (C) unlocked at

position A.

FILLING THE SYSTEM

2

1

4

3

6

5

B

A

C

B

A

C

1 - 2 bar

F

D

E

E

Total system

volume (litres)

180

107

138

Initial system

pressure (bar)

0.5

1.0

1.0

Initial charge

pressure (bar)

0.5

0.5

1.0

Advertising
This manual is related to the following products: