9 shut down and park, 10 lifting and tie down – JLG 800A_AJ Operator Manual User Manual

Page 75

Advertising
background image

SECTION 4 - MACHINE OPERATION

3121209

– JLG Lift –

4-13

4.9 SHUT DOWN AND PARK

1. Drive machine to a protected area.

2. Assure main boom is fully retracted and lowered over

rear (Drive) axle; all access panels and doors closed
and secured.

3. Remove all load and allow engine to idle 3-5 minutes to

permit reduction of engine internal temperatures.

4. At Ground Controls, turn KEY SELECT switch to (center)

OFF. Position, POWER/EMERGENCY STOP switch
(down) to OFF. Remove key.

5. Cover Platform Control console to protect instruction

placards, warning decals and operating controls from
hostile environment.

4.10 LIFTING AND TIE DOWN

When transporting machine, boom must be in the stowed
position mode, (booms lowered and retracted) with turntable
lock pin engaged, and machine securely tied down to truck
or trailer deck. Six tie down eyes are provided in the frame
slab, one at each corner of the machine and 2 holes at the
center of the frame. (See Figure 4-5., Machine Tie Down)

If it becomes necessary to lift the machine using an over-
head or mobile crane, it is very important that the turntable
lock pin is engaged, lifting devices are attached only to the
designated lifting eyes, and spreader bars are to be used to
prevent damage to the machine. (See Figure 4-6., Lifting
Chart f
or gross machine weights.)

NOTE: When transporting machine over rough terrain or long dis-

tance, the boom needs to be chocked and strapped. This
prevents the boom from bouncing up causing possible
damage.

Advertising