SECTION 6 - GENERAL SPECIFICATIONS & OPERATOR MAINTENANCE

6-12

– JLG Lift –

3121217

6.4

OSCILLATING AXLE LOCKOUT TEST (IF
EQUIPPED)

LOCKOUT SYSTEM TEST MUST BE PERFORMED QUARTERLY, ANY
TIME A SYSTEM COMPONENT IS REPLACED, OR WHEN IMPROPER
SYSTEM OPERATION IS SUSPECTED.

NOTE:

Ensure boom is fully retracted, lowered, and centered
between drive wheels prior to beginning lockout cylinder
test.

1. Place a 6 inches (15.2 cm) high block with ascension

ramp in front of left front wheel.

2. From platform control station, start engine

3. Place the Drive control lever to the forward position and

carefully drive machine up ascension ramp until left front
wheel is on top of block.

4. Carefully activate Swing control lever and position boom

over right side of machine.

5. With boom over right side of machine, place Drive con-

trol lever to Reverse and drive machine off of block and
ramp.

6. Have an assistant check to see that left front or right rear

wheel remains elevated in position off of ground.

7. Carefully activate Swing control lever and return boom

to stowed position (centered between drive wheels).
When boom reaches center, stowed position, lockout
cylinders should release and allow wheel to rest on
ground, it may be necessary to activate Drive to release
cylinders.

8. Place the 6 inches (15.2 cm) high block with ascension

ramp in front of right front wheel.

9. Place Drive control lever to Forward and carefully drive

machine up ascension ramp until right front wheel is on
top of block.

10. With boom over left side of machine, place Drive control

lever to Reverse and drive machine off of block and
ramp.

11. Have an assistant check to see that right front or left rear

wheel remains elevated in position off of ground.

12. Carefully activate Swing control lever and return boom

to stowed position (centered between drive wheels).
When boom reaches center, stowed position, lockout
cylinders should release and allow wheel to rest on
ground, it may be necessary activate Drive to release
cylinders.

13. If lockout cylinders do not function properly, have quali-

fied personnel correct the malfunction prior to any fur-
ther operation.