Commissioning steps, 7commissioning – Lenze E82ZAFIC001 User Manual

Page 52

Advertising
background image

7

Commissioning

Commissioning steps

EDK82ZAFIC−001 DE/EN/FR 5.0

52

l

H2_Inbetriebnahmeschritte−inbetrieb_DE

Commissioning steps

)

Note!

Do not change the setting sequence.

Step−by−step commissioning of the function module with the DRIVECOM device control is
described below.

Step

Procedure

Detailed
information

1.

Configure the host (master) for communication via the function
module.

^ 54

2.

Inhibit the standard device via terminal 28 (CINH).

l

Set terminal 28 to LOW level.

l

Later on the standard device can be inhibited and enabled via the
bus system.

Documentation
for the standard
device

3.

Set DIP switch S1:

l

Setting for the last node = OFF

l

Setting for all other nodes = ON

^ 57

4.

Define user data length via ...

l

DIP switches S2 ... S4 or

l

code C1515

^ 55

5.

Connect the mains voltage and, if available, the separate voltage
supply for the function module.

l

The standard device is ready for operation after approx. 1 second.

l

Controller inhibit (CINH) is active.

^ 58

Response

l

The green LED "Connection status to standard device" at the front
of the function module is lit (only visible in the case of the 8200
vector).

l

Keypad:

dc

(if attached)

^ 59

6.

It is now possible to communicate with the standard device, i.e. all
codes can be read and all writable codes can be adapted to the
application.

Documentation
for the standard
device

Response
The yellow LED on the function module is blinking when the
INTERBUS is active.

^ 59

7.

If PCP communication is used, carry out the PCP service "initiate".

l

It is now possible to access the parameters of the standard device
with the PCP services "read" and "write".

INTERBUS
communication
manual