Installing the FD86N Enclosure

2-9

Publication S-3062 – November 1997

Installing a Pull Box to a
Bus Bar Enclosure

Hardware needed:

Six M6 or ¼-20 thread-forming screws.

To install a pull box to the bus bar enclosure:

1. Remove the split or top access cover from the pull box. Refer to

Figure 2.7.

2. Place the pull box on the bus bar enclosure over the cutout.

3. Align the mounting holes. Refer to Figure 2.7.

4. Fasten the pull box to the bus bar enclosure using the M6 or ¼-20 thread-

forming screws.

5. Reinstall the access covers.

Figure 2.7
Installing a Pull Box to a Bus Bar Enclosure

Split Access Cover

Top Access Cover

Bus Bar Enclosure

Typical 27

High Pull Box

Typical 9

High Pull Box

Typical 18

High Pull Box

Cutout

Typical Pull Box
(Access Covers
Removed)

Split Access Cover

Advertising