Installing the FD86N Enclosure
2-9
Publication S-3062 – November 1997
Installing a Pull Box to a
Bus Bar Enclosure
Hardware needed:
•
Six M6 or ¼-20 thread-forming screws.
To install a pull box to the bus bar enclosure:
1. Remove the split or top access cover from the pull box. Refer to
Figure 2.7.
2. Place the pull box on the bus bar enclosure over the cutout.
3. Align the mounting holes. Refer to Figure 2.7.
4. Fasten the pull box to the bus bar enclosure using the M6 or ¼-20 thread-
forming screws.
5. Reinstall the access covers.
Figure 2.7
Installing a Pull Box to a Bus Bar Enclosure
Split Access Cover
Top Access Cover
Bus Bar Enclosure
Typical 27
″
High Pull Box
Typical 9
″
High Pull Box
Typical 18
″
High Pull Box
Cutout
Typical Pull Box
(Access Covers
Removed)
Split Access Cover