CDV Series Direct Vent Gas Fireplace

20010175

Vertical Through-the-Roof Applications

CFM148

Maximum

10’

(3 m)

Minimum

8’ (2.4 m) /

Maximum

40’ (12 m) Vertical

Rise

CFM148

Pipe Straps Every

3’ (914 mm)

Fig. 33 Support straps for horizontal runs.

This Gas Fireplace has been approved for:
1. Vertical installations up to 40’ (12 m) in height. Up to

10’ (3 m) horizontal vent run can be installed within
the vent system using a maximum of three 90°
elbows.

2. Up to two 45° elbows may be used within the

horizontal run. For each 45° elbow used on the
horizontal level the maximum horizontal length must
be reduced by 18” (457 mm).

Example: Maximum horizontal length
0 x 45° elbows = 10’ (3 m)
1 x 45° elbows = 8¹⁄₂’ (2.6 m)
2 x 45° elbows = 7’ (2.1 m)
3. A minimum of an 8’ vertical rise.
4. Two sets of 45° elbows offsets within these vertical

installations. From 0 to a maximum of 8’ (2.4 m) of
vent pipe can be used between elbows. (Fig. 34)

5. 7DVCS must be used to support offsets. (Fig. 34)

This application will require that you first determine
the roof pitch and use the appropriate 7DVSKV (A, B
or F). (Refer to Venting Components List, Page 27)

FP1021

Typical vertical

through the roof

application

3/26/00 djt

Max.

8’

(2.4 m)

45°

Max.

8’

(2.4 m)

45°

50’

(15 m)

Typical
Ceiling

Support

Application

Typical Roof

Support Ap-

plication

FP1021

Typical Offset Installation

Fig. 34 Typical vertical roof applications.

Vertical Through-the-Roof Installation

1. Locate your fireplace.
2. Plumb to center of the (4”) flue collar from ceiling

above and mark position.

3. Cut opening equal to 9³⁄₈” x 9³⁄₈” (240 x 240 mm).
4. Proceed to plumb for additional openings through

the roof. In all cases, the opening must provide a
minimum of 1 inch clearance to the vent pipe, i.e.,
the hole must be at least 9³⁄₈” x 9³⁄₈” (240 x 240 mm).

5. Place fireplace into position.
6. Place firestop(s) #7DVFS or Attic Insulation Shield

#7DVAIS into position and secure. (Fig. 35)

CFM100

Firestop-Vertical

09/20/00

11"

11"

Joist

Joist

Firestop Spacer

Nails (4)

Upper Floor

Attic Insulation
Shield

Ceiling
Installation

CFM100

Fig. 35 Place firestop spacer(s) and secure.

If there is room above ceiling level,
firestop spacer must be installed on both
the bottom and the top side of the ceiling
joists. If an attic is above ceiling level a
7DVAIS (Attic Insulation Shield) must be
installed. (Fig. 35)