CDV Series Direct Vent Gas Fireplace

20010175

Below Grade Installations

When it is not possible to meet the required vent ter-
minal clearances of 12” (305 mm) above grade level a
snorkel vent kit is recommended. It allows installation
depth of down to 7” (178 mm) below grade level. The
7” is measured from the center of the horizontal vent
pipe as it penetrates through the wall.

If venting system is installed below
ground, we recommend a window well with
adequate and proper drainage.

Ensure sidewall venting clearances are observed.
If installing a snorkel a minimum 24” (610 mm) vertical
rise is necessary. The maximum horizontal run with
the 24” (610 mm) vertical pipe is 36” (914 mm). This
measurement is taken from the collar of the fireplace (or
transition elbow) to the face of the exterior wall. Refer to
the Sidewall Vent Graph for extended horizontal run if
the vertical rise exceeds 24” (610 mm).
1. Establish vent hole through the wall. (Fig. 44)
2. Remove soil to a depth of approximately 16” (406 mm)

below base of snorkel. Install drain pipe. Install win-
dow well (not supplied). Refill hole with 12” (305 mm)
of coarse gravel leaving a clearance of approximately
4” (102 mm) below snorkel. (Fig. 49)

3. Install vent system.
4. Ensure a watertight seal is made around the vent pipe

coming through the wall.

5. Apply high temperature sealant caulking around the 4”

and 7 “ snorkel collars.

6. Slide the snorkel into the vent pipes and secure to the

wall.

7. Level the soil to maintain a 4” (102 mm) clearance

below snorkel. (Fig. 49)

BG402a

Top Vent

Below grade installation

1/26/00 djt

Firestop

7” Pipe

7TDVSNORK

(Snorkel)

4” (102mm)

Clearance

Min.

Window

Well

Gravel

Drain

BG402

Fig. 49 Below grade installation.

Zero Clearance Sleeve

(if required)

*A minimum of 24” (610mm) ver-

tical pipe must be installed when

using the 7TDVSNORK Kit.
*The 22” (559mm) vertical rise

(center to center) of the snorkel

may be included for calculationof

max. horizontal run.

24” (610mm)

Minimum*

Screws

Foundation Wall

Do not back fill around snorkel. A clearance
of at least 4” (102 mm) must be maintained
between snorkel and the soil.

If the foundation is recessed, use recess brackets (not
supplied) for securing lower portion of the snorkel.
Fasten brackets to wall first, then secure to snorkel
with self drilling #8 x 1/2 sheet metal screws. It will be
necessary to extend vent pipes out as far as protruding
wall face. (Fig. 50)

BG401

Snorkel

2/10/99 djt

Foundation Recess

Snorkel

Wall Screws

Recess Brackets

Watertight Seal

Around Pipe

Sheet Metal

Screws

BG401

Fig. 50 Snorkel installation, recessed foundation.

Vertical Through-the-Roof Applications

This Gas Fireplace has been approved for:

Vertical installations up to 40’ (12 m) in height. Up
to a 10’ (3 m) horizontal vent run can be installed
within the vent system using a maximum of two 90°
elbows. (Fig. 51)

Up to two 45° elbows may be used within the
horizontal run. For each 45° elbow used on the
horizontal level the maximum horizontal length must
be reduced by 18” (457 mm).

Example: Maximum horizontal length
0 x 45° elbows = 10’ (3 m)
1 x 45° elbows = 8¹⁄₂’ (2.6 m)
2 x 45° elbows = 7’ (2.1 m)

A minimum of an 8’ (2.4 m) vertical rise.