I C R - 2 2 5 - I N S T A L L A T I O N M A N U A L

Figure 20

Horizontal Mullion Fabrication

Figure 21

Horizontal Installation

FS-55 (#10 X 1/2" PPH)

1/2"

Locate on

V-Groove

#25 ( .149”) Dia. tap

hole for #10 screw

(centered on V-Groove)

Drop Horizontal over

Shear Block then

push back to lock

See Page 17 for the

required application of

sealant prior to installation

of Horizontal

Keep hook area free from

sealant for glazing bead

installation

5.6

Horizontals can be attached either before or after the frame is installed in the opening. Prior to

attaching intermediate horizontals, apply sealant to the face of shear block and along outer face of

mullion where horizontal will intersect the face. Roll the horizontal over the shear blocks and attach

with (1) FS-55 #10 x ½” Phillips Pan Head screw.

See Figure 20 & 21.