I C R - 2 2 5 - I N S T A L L A T I O N M A N U A L

NOTE: Structural silicone glazed vertical mullion is referred to as “SSG Mullion.”

Details in this manual reflect the 4 1/2” system. 6” system part numbers and dimensions are referenced

in parentheses ( ) where applicable.

FRAME FABRICATION TYPE “A”

1.1 Measure Rough Opening to determine Frame Width and Frame Height dimensions. Allow 1/2” minimum

clearance for shimming and caulking around perimeter of frame.

1.2 Cut material to size.

SEE FIGURE 5 for guide.

Material Fabrication Guide

Figure 5

Frame Width

D.L.O.

Bay Width

at SSG Mull

D.L.O.

Frame

Height

Glazing gaskets should be cut 1/4” longer per foot of aluminum extrusion. Set aside and lay flat until

ready to glaze.

Head and Sill
Verticals, vertical filler and jambs

Vertical Face Caps

Intermediate Horizontals

(Optional) Intermediate Horizontals

Horizontal Glass Stops
Horizontal Face Caps
Horizontal Face Caps @ SSG

Daylight Opening (D.L.O.)
Frame Height

Frame Height

D.L.O. (Screw Spline)
D.L.O. Minus 1/16” (Shear Block)
D.L.O. Minus 1/32”
D.L.O. Minus 1/16”
Bay Width Minus 1/16” (SEE FIGURE 5)

(Maximum length 3 lites or 15 feet)