Flush-Mount Installation

The two-post rack kit is shipped with the brackets configured for center-mount installation.
To prepare the slide assemblies for flush-mount installation in the two-post rack, perform

the following steps:

1

Locate the two slide assemblies and place them, side by side, on a smooth work

surface, with the front ends of the slide assemblies toward you. Position both slide
assemblies so that the center brackets are facing upward (see Figure 1-16).

^ NOTE:

To prepare the slides for flush-mount installation, remove the front

mounting bracket, rotate it 180 degrees, and reinstall it on the opposite slide

assembly.

2

Using a #2 Phillips screwdriver and an 11/32-inch wrench or nut driver, remove two

12-24 X 0.5-inch pan-head Phillips screws, two nuts, and two shoulder washers from

each front center bracket (see Figure 1-16).

3

Remove the front bracket from both slide assemblies.

+

Place the bracket from one slide assembly onto the threaded studs on the opposite

slide assembly, with the bracket turned 180 degrees so that the mounting flange faces
forward (see Figure 1-16).

5

Secure each front center-mount bracket (by its nuts and shoulder washers) by finger­

tightening them on their opposite slide assemblies using the two shoulder washers and
two nuts you removed in step 2 (see Figure 1-16).

The joined bracket becomes the new extended back bracket.