9 ac electrical power wiring – AERCO BMK 1500-2000 User Manual

Page 24

Advertising
background image

Benchmark 1500 - 2000 Boilers

CHAPTER 2 – INSTALLATION

Page 24 of 188

AERCO International, Inc. • 100 Oritani Dr. • Blauvelt, NY 10913

OMM-0097_0D

Ph.: 800-526-0288

GF-142

2.9 AC ELECTRICAL POWER WIRING

The AERCO Benchmark Electrical Power Wiring Guide, GF-2060, must be consulted prior to
connecting any AC power wiring to the unit. External AC power connections are made to the
unit inside the Power Box on the front of the unit. Remove the front panel to access the Power
Box, which is mounted in the upper right corner of the unit as shown in Figure 2-8. Loosen the
two upper screws of the Power Box cover and remove cover to access the internal connections
shown in Figure 2-9.

Figure 2-8: Power Box Location with Cover Closed

THE POWER BREAKER SHOWN IN FIGURE 2-9 DOES NOT
REMOVE POWER FROM THE TERMINAL BLOCKS.

Figure 2-9: Power Box Internal Components

With the exception of the transformer shown in Figure 2-9, all of the components in the Power
Box are mounted on a DIN rail.

WARNING

12V POWER

SUPPLY

FUSE BLOCKS (2)

TERMINAL BLOCKS

POWER
BREAKER

TRANSFORMER

WIRE CONDUITS

24V POWER

SUPPLY

Advertising