INSTALLATION

2-1

SECTION 2 - INSTALLATION PROCEDURES

2.1. RECEIVING THE UNIT

Each KC1000 Boiler is shipped as a single

crated unit. The crated shipping weight of the

unit is approximately 1500 pounds, and must be

moved with the proper rigging equipment for

safety and to avoid damages. The unit should be

completely inspected for shipping damage and

completeness at the time of receipt from the

carrier and before the bill of lading is signed.

Each unit has Tip-N-Tell indicator on the outside

of the crate that indicates if the unit has been

turned on its side. If the Tip-N-Tell indicator is

tripped, do not sign for the shipment. Request a

freight claim and inspection by a claims adjuster

before proceeding or refuse delivery of the

equipment.

2.2. UNPACKING

Carefully unpack the unit. Take care not to

damage the unit jacket when cutting away

packaging materials. An inspection of the unit

should be made to determine if damage during

shipment occurred that was not indicated by the

Tip-N-Tell. The freight carrier should be notified

immediately if any damage is detected. The

following accessories come standard with each

unit and are packed separately within the unit’s

packing container

Spare Spark Ignitor

Spare Flame Detector

Manual 1-1/4" Gas Shutoff Valve

Drain Valve Assembly

ASME Pressure Relief Valve

Differential Regulator Spring:

P/N 122548 (Propane) or

P/N 124803 (Natural Gas)

Ignitor Removal Tool (One per Site)

Temperature/Pressure Gauge and

Fittings

2 Lifting Lugs

Stainless Steel Condensate Cup

Shell Cap

Wing Nut for Shell Cap

Optional accessories are also separately packed

within the unit’s packing container. Standard and

optional accessories shipped with the unit

should be identified and put in a safe place until

installation or use.

Figure 2.1. Boiler Clearances