Inspect and Clean the

Burner

With the burner assembly removed, shine a flashlight on the burner ribbons. Look for

carbon buildup, scale, dust, lint, and/or anything that might restrict flow through the

spaces between the burner ribbons. Holding the burner assembly so that any foreign

material will fall away from the burner, use a stiff bristle brush to loosen and remove

any foreign material(s). If the burner is excessively dirty, remove one of the burner end

caps. Remove the four screws that hold the end cap to the burner housing. Lightly tap

the end cap to remove it.
Clean all foreign material from the burner and venturi. After the burner is thoroughly

clean, replace the end cap making certain that it is tight against the burner housing.

NOTE: If any of the burner components are damaged or deteriorated, replace the

burner assembly.

Inspect the Lower Portion of the Heat Exchanger (with burner assembly

removed)

At the burner flame entrance of each tube, shine a bright light into each heat exchanger

section. With the light shining into the heat exchanger, observe the outside for visible

light. Repeat this procedure with each heat exchanger section. If any light is observed,

replace the heat exchanger.

Re-Install the Burner

Instructions to Re-Install the Burner (Refer to FIGURE 19)

1. Attach the Burner Assembly - Holding the venturi tube, slide the entire burner

assembly into position. Align the supports on the left side with the slots in the

burner shield; sliding the supports into the slots. On the right, re-attach each

burner body support to the secondary air shield.

2. Attach the Secondary Air Baffles (Sizes 60-400 only) - Re-attach the secondary

air baffles as marked. Baffles may be different sizes and each

must be attached in

the correct location.

3. Attach the Control Assembly - Carefully slide the control assembly into position.

Re-attach with the same screws. Check to be sure all wire connections are secure.

4. Attach the Gas Train - Slide the gas train so that the orifice adapter is through

the bracket. Fasten the gas train to the bracket with the locking nut. Install the gas

orifice. Re-connect the wires to the gas valve.

5. Close the access panel.
6. Reconnect the gas supply at the union outside of the cabinet. Leak test the

connection with leak detecting solution.

7. Turn on the electric and the gas. Check for proper operation.

10.2.3 Burner Orifice

Burner orifice usually only needs to be replaced when installing a gas conversion kit. If

ordering a replacement orifice only, give BTUH content and specific gravity of gas, as

well as the model and serial number of the unit. When removing or replacing the burner

orifice, be careful not to damage the venturi tube and/or the bracket.

10.2.4 Ignition System

DSI Integrated Control Module (circuit board) - See FIGURE 20. The module moni-

tors the operation of the heater including ignition. The only replaceable component is

the 3 amp Type ATC or ATO fuse. If the fuse is blown, the problem is most likely an

external overload. Correct the problem and replace the fuse.

FIGURE 20 - DSI

Integrated Control

Module (Circuit Board)

Only

replaceable

part is a Type

ATC or ATO 3

amp fuse (Color

Code Violet),

P/N 201685

Advertising