SEPARABLE UNION

PIPING BY CARRIER
FIELD PIPING

1. Connect dehydration pump to cooler charging

valve.

2. Ensure that all valves on purge assembly are

closed; valves on filter-drier system open.

3. Install mercury manometer (absolute pressure

type) at charging valve.

4. Operate pump until manometer reads 0.20 in.

Hg absolute. Continue to operate pump for 2
more hours.

5. Close cooler charging valve; stop pump; record

manometer reading.

6. Wait 2 hours and read manometer again. If ab­

solute pressure reading has not increased, dehy­
dration is complete. If absolute pressure has
increased, repeat steps 4, 5 and 6.

7. If vacuum fails to hold after several dehy­

dration attempts, check for machine leak by
repeating the (?heck for Small Leaks.

Pumpout Procedures

(R-114 Units)

MACHINE EVACUATION (No refrigerant in
system)

1. Set purge valves per Operation 5 on purge valve

operation plate.

2.

Jumper low-pressure cutout on pumpout

compressor.

3. Close valves 1, 3, 7 and 10.
4. Open valves 2, 4, 5, 6, 8, 9 and 11
5. Disconnect separable union between pumpout

condenser and oil separator.

6.

Run

pumpout

compressor

until

desired

machine vacuum is reached.

7. Close valve 5 and reassemble union.
8. Stop compressor.
9. Remove jumper.
PRESSURIZING THE MACHINE (No refrigerant
in system)

1. Set purge valves per Operation 4 on purge valve

operation plate.

2. Close valves 2, 4 and 10.
3. Open valves 1, 3, 5, 6, 7, 8, 9 and 1 1.
4. Disconnect separable union in pumpout com­

pressor suction Hne.

Fig. 3 — Pumpout System Schematic (R-114 Units)

5. Operate pumpout compressor until desired

pressure is reached. Do not exceed test pressure
listed in Table 1.

6. Shut off pumpout compressor
7. Reassemble union.
8. Return purge valves to “Normal-Auto” condi­

tion when pressurizing is completed.

Oil Charge

— Use oil shipped with machine. This

oil conforms to Carrier’s oil specifications for
hermetic centrifugal compressors.

Charge oil thru the oil reservoir charging valve.

Machine vacuum will draw the oil from the

container. Add oil until it reaches the middle of
the oil sight glass. After charging, close valve

completely to prevent air from entering machine.
R-114 machines containing refrigerant will require
a small hand pump for oil charging.

On pneumatic machines, add oil to the vane seal

chamber thru pipe plug opening (see Fig. 4) until
level reaches bottom of rack and gear as seen thru

Plexiglas cover.

Oil Heater

— Check for 1 20 volt supply. Energize

oil heater to minimize oil-refrigerant absorption. A
light indicates when the heater is energized. The oil

heater thermostat is set to maintain a temperature
of 140 F ± 3 F at shutdown. Adjust if required.

Fig. 4 — Pneumatic Vane Shaft Seal Chamber