3 power block, 5 installation, 1 preparation – CIRCUTOR FRE Series User Manual

Page 10: 2 installation location, Installation, Reparation, Nstallation location

Advertising
background image

FRE / FRES

10 / 20

4.6.3 Power block:

The power block of

FRE or FRES units is made up of 3 to 12 thyristors + capacitor groups, depending on

the type. Each group consists of a 6-terminal capacitor (three single-phase capacitors), three (*) thyristor

modules attached to a cooling heatsink, one

RBE reactor for each step and the suitable protection

elements addapted to the module's rated power.

(*) On some models the three thyristor modules are integrated into a single encapsulated package

5

INSTALLATION

5.1 Preparation

FRE and FRES CIRCUTOR's static filters are prepared for an easy installation and start-up.
Remove the equipment's packaging and verify that the unit's electrical characteristics are suitable for

connection to the available grid. For this, check the characteristics label located inside the cabinet, next

to the regulator, refer to Fig. 4-1 as an example. Key data to be checked:

- Grid voltage and mains frequency, U

n

/ f.

- Nominal power of the capacitor bank, Q

n

(kvar) and composition

- Type of filter, identified by the p% factor (7%, 14%, ..., etc.)

- Current consumption, I

max

(See label). This current must be considered to select the proper size

of the equipment's power supply cable and ultimately the main switch or the external circuit

breaker to protect the equipment.

- Auxiliary control voltage, U

aux

(See section 5.3.3)

- Environmental conditions. (See section 4.3)

5.2 Installation location

For static switching equipment it is specially important to maintain a minimum distance around the

equipment to facilitate cooling. In self-supporting cabinets, the back and front sides of the cabinet must

be kept at least 50 cm away from walls and other equipment. Regarding the sides, it is recommended

that a separation of 10 cm to be maintained between adjacent equipment. On wall mounted cabinets, it

is recommended that at least 20 cm of separation be maintained between the sides of adjacent

equipment.

NOTE: Static units have one or more aluminium heatsinks for cooling the thyristors.

Periodically clean these heatsinks with a brush or with compressed air and ensure

that they have maximum ventilation.

Make sure the equipment can be accessed easily.
The environmental conditions of the location where the equipment is installed must not surpass the

limits established in the technical characteristics (See section -

)

To ensure proper ventilation, the unit must be installed in a vertical position.
In accordance with most National Electric Codes and LVD, once the unit is installed, it must be

protected against electric shock hazard due to direct or indirect contacts; therefore, a circuit breaker and

an earth leakage protection relay should be provided for the capacitor bank's supply line.

5.3 Connection of the capacitor bank with filters to the grid

Check that the nominal voltage of the capacitor bank with filters matches the voltage

between phases of the grid where it is being connected. Also check the auxiliary

circuit voltage (CPC controllers). For this, refer to section 5.3.3
For feeding cables into the capacitor bank cabinet, always use the entry points

available for this purpose.
Do not drill holes into the cabinet for feeding cables through them or for installing

support brackets. Drilling produces metal shavings that may enter the contacts or

other devices and cause short-circuits.

Advertising