Installing the device
1. Mark the positions of the drill holes using the cut-outs in the mounting plate.

NOTE: The minimum clearances between two devices, or the device and the ceiling/floor have already been

taken into account in the diagram.

2. Fix mounting plate to the wall with the supplied mounting fixtures.

Make sure that the mounting plate is oriented correctly.

3. Hang the device on the mounting plate using the suspension brackets on the back of the housing.
4. Fix the device into position using the transport bolt supplied.

»

The device is installed. Continue with the installation.

NOTE

An installation carried out and approved by specialist company authorised and certified by KACO

offers you the advantage of an extended warranty for the device.

7

Installation

7.1

Preparations for installation

Line cross-sections for connection terminals

Cable cross-sec-

tion

Length of insulation to be

stripped off

AC-source

6 - 16 mm²

16 mm

AC-load

6 - 16 mm²

16 mm

Battery (B+, B-)

50 - 70 mm²

20 mm

Precharge B+,B-,Mid

0.75 - 2.5 mm²

12 mm

External C.T.

0.5 - 2.5 mm²

12 mm

I/O card (digital inputs/outputs, changeover contacts, 12V

power supply)

0.25 - 0.75 mm²

12 mm

Table 3:

Line cross-sections/tightening torque for connection terminal

NOTE

Use copper wires for all electrical connections. (With wire sleeves if required)

During connection work, ensure that no insulation is trapped and/or stuck.