Figure 63: Top brick panel in place, screws shown.

Figure 64: Back brick panel in place.

Figure 65: Side brick panels in place.

Figure 62: Brick panel bracket, slots shown.

1. Remove the two (2) screws from the

rear of the baffle, use a ¼” socket

or a flat head screwdriver. Place the

provided brick bracket (Figure 62) at

the rear of the baffle with the slots

over the screw holes (see Figure 63).

Insert two (2) of the provided screws

into the two (2) holes along the

bottom of the baffle.

2. Remove the two (2) screws from the front of the

baffle. Slide the top brick panel into the bottom

bracket and place the other brick bracket over the top

of the panel and line up the slots on the bracket with

the holes at the top of the baffle. Use two (2) of the

provided screws to hold the bracket in place. Ensure

the top panel is centered before tightening the four

(4) screws completely (refer to Figure 63).

3. Slide the bottom brick panel into place under/behind

the top panel bracket, the notched side is to rest on

the firebox bottom. The panel should rest flush with

the back of the firebox (refer to Figure 64).

4. Slide each side brick panel into place along the sides

of the firebox. The panels should rest flush with the

back panel and the sides of the firebox (refer to

Figure 65).

Secondary Installation

i

nstaLLation

oF

P

aneL

s

et

:

Do not install when the unit is hot.

The brick panel set is fragile. Handle panels with care and avoid knocking them on the