3-INSTALLATION AND ASSEMBLY
The product can be installed at the desired height by constructing a suitable platform. This support must be made of non-flammable
material.
The company declines all liability for any damage to objects and persons if the above-mentioned precautions are not
complied with.
REMOVING THE COMPENSATION FRAME
In order to prevent damaging the finishing frame (C) around the door, it is recommended to remove it before fastening the product to the
base (E) and set in a safe place.
FITTING THE PELLET LOADING CHUTE
The side on which the fuel loading chute is to be installed must be decided upon before setting the product in place. The VIVO 80 PELLET
is delivered with two clamps, the connection pipe and the chute with a door.
The chute can be fitted on the right, left or at the front. The connection pipe is 1 metre long.
The connection pipe must be shortened according to its position (side or front) for it to be taut and form a slight
angle from the horizontal line. This is required for the pellets to go down.
Before applying the cladding, run a fuel loading test to make sure the fuel descends properly to the hopper.
The pipe must be insulated properly if this is fitted on the left side, in correspondence with the smoke expulsion.
The manufacturer declines all liability if the above mentioned warning is not complied with.
Fire hazard!!
D = SUPPORT
E = BASE
B = SCREW
C = FRAME