3-INSTALLATION AND ASSEMBLY

PRODUCT INLET HOLE

The hole made on the wall must be 765*610 mm. These measurements allow the frame to cover the gap that remains between the

product and the hole and also allow the product to be removed if maintenance is to be performed and/or parts are to be replaced.

FITTING THE CHUTE AT THE FRONT

Proceed as follows if the pipe is to be positioned at the front:

• Connect the supplied pipe to the product, making sure it is turned to the front, and fasten it with the clamp.

• Connect the pipe to the opening of the door structure with the supplied clamp.

• Position the pipe in such a way that it is accessible once the cladding is completed and for the door structure to be fastened to the

preset hole on the wall of the cladding itself.

• Refer to the relative paragraph to fit the external door, since this is to be carried out once the cladding is completed.

CONNECTING THE SWITCH AND CONTROL PANEL

The control panel and switch are already fitted on the pellet loading door and connected to the respective wires by the manufacturer.

Connect the wire of the switch to the socket on the rear side of the product.

The wire of the control panel must be connected to the electric board in position 1. T

o fix the switch to the pellet loading hatch one must temporarily disconnect the cables. Reconnect the cables to the relative terminals as

shown in the figure.

N = BLACK

R = RED

B = BLUE

M = BROWN